From sales rate to order quantity, step by step, with a worked example and what each "Why" reason means.
Every night the app recalculates each product in four steps: how fast it sells, how much you need to cover the wait for new stock, when to order, and how much to order. Everything below is visible on the product's page, under How it sells and Why.
The sales rate is units sold per day — but per day in stock, not per calendar day. If a product sold 30 units in a month but was out of stock for half of it, its rate is 2 per day, not 1. Dividing by days it could not sell would make a popular product look slow, and you would under-order exactly what sells best.
How it is measured:
On the product page, Sales rate is the blended rate; Last 28 days and Last 90 days show the two longer windows, and Days in stock how many of those days it could actually sell. The badge next to the rate — Accelerating, Slowing or Steady — compares the last 28 days with the last 90. It is for information only: the recent weeks are already weighted in the rate.
With at least 12 months of history, the app learns how much each month sells compared to an average month, per product type (not per product: one product's history is usually too thin). The forecast is then adjusted for the months your order has to cover. An order placed in October that must last through December plans for December.
Without 12 months of history the forecast assumes every month is the same, and says so with No seasonality yet. On the product page, Seasonality shows the factor applied (1.40× means 40% above an average month) or Flat.
The reorder point is the stock level at which you have to order, because what is left will only just last until the new stock arrives:
reorder point = sales rate × lead time (adjusted for season) + safety stock
Safety stock is the cushion for days that sell more than usual. It grows with how irregular the product's sales are and with the lead time, and with the product's class: it aims to avoid running out 98% of the time for class A products, 95% for B and 85% for C. A product that sells exactly the same every day needs almost none.
The lead time comes from the supplier. See Suppliers and lead times.
The order has to last until it arrives and until your next order arrives after it:
target stock = sales rate × (lead time + order cycle) × season + safety stock
order = target stock − available − already on order
Then two supplier rules are applied, in this order:
Units already on open purchase orders (sent, in transit or partly arrived) are subtracted, so you are never asked to buy the same stock twice. Drafts are not subtracted: a draft is not an order until you send it.
The order-by date is the day your stock is expected to reach the reorder point at the current rate. If you are already there, the date is today and it shows in red.
Days of cover is simpler: available stock divided by the sales rate. It does not count units on order.
A product sells 2 per day. The supplier takes 14 days to deliver, you order from them every 30 days, they ship in cases of 12. Safety stock works out at 10 units. You have 60 in stock and nothing on order.
Each product shows the reasons behind its numbers. On the supplier's page they are behind the N reasons badge; on the product page they are listed with an explanation.
| Reason | What it means |
|---|---|
| Stockout adjusted | It was out of stock some days; the rate only counts days in stock. |
| Estimated stockouts | Some of those out-of-stock days were deduced from long gaps in sales, because Shopify keeps no stock history from before you installed. We only count a gap when it is clearly a stockout. |
| Spike smoothed | A very high day was capped. |
| Accelerating / Slowing | Selling faster or slower in the last 28 days than in the last 90. |
| Seasonality applied | Adjusted for the months the order will cover. |
| No seasonality yet | Less than 12 months of history; seasons are not considered. |
| Limited history | The app can only read 60 days of orders, so seasons are not visible. |
| Estimated lead time | The supplier is on the 14-day default. Confirm the real one. |
| High returns | 15% or more of the units sold came back. The forecast uses what was kept. |
| Backorder | It sells while out of stock, so negative stock is not treated as a stockout. |
| New product | Less than 28 days old. |
| Estimated from similar | No sales yet; the rate comes from its other variants. |
| No history | No sales and nothing to compare with. No quantity is suggested. |
| Dead stock | In stock but no sales in 90 days. No quantity is suggested. |
When a product shows a dash instead of a quantity, it is one of the last two: we would rather show nothing than a number with nothing behind it.